CAR POLICY: CONTRACTOR ALL RISK POLICY
one type of insurance
Virtual completion period: Time
duration for work/project.
Successful completion: It's complete on defected liability
period (around after 12month after completion of project).
Amount of CAR
POLICIES = alloted work cost (1 cr.) + 15% = 1.15 Cr. Amount Car policies
required vaild till to virtual completion period.
Required to Basic
Cover in CAR POLICIES
Earthquake
Fire/explosion
Collapse
Strom/cyclone
Flood
Landslide
Loss or damage due to riot and civil commotion(SRCC)
Pilferage, Burglary and Theft
ADD ON COVERS
Debris removal (add on cover) in case of building collapse
and earthquake.
Act of terrorism
Contractor Plant and Machinery
Limited extended maintenance cover
Free issue of the material issue by client
Third-party insurance including cross liability – legal liability for fatal and non-fatal injuries caused to a third person (other than the own employee or workers insured) due to the
construction of property/project. Minimum amount 1 cr.
Damage to owner's surrounding property – Legal liability for accident damage or loss caused to the
property/asset of the third person due to construction.
Workman’s
Compensation Insurance Policy to cover contractor liability under workmen’s
compensation Act 1923, minimum wages Act 1948, Contractor labour (Regulation and
Abolition) Act 1970 and other relevant Acts listed elsewhere. This shall be valid
for the period upto final completiton of the work and any extension thereof.